GRE Math Numeric Entry Question 188

Home > GRE Test > GRE Math Numeric Entry Questions

Next steps

Source: Other

Noah's contracting company builds road at a rate of 1 mile per week, except during the rainy season, when that rate drops to mile per week. If Noah is hired to build 11 miles of road, and his company begins construction 5 weeks before the start of the rainy season, how many weeks will it take Noah's company to complete the contract? (Rainy season lasts 14 weeks.)

Show Answer

Previous       Next