A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into 12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?

  • A 380
  • B 540
  • C 1050
  • D 1380
  • E 1430